Subcontract Agreements in Saudi Arabia: Clauses That Prevent Payment Disputes
Content updated · About Abdullah Almendaha, licensed Saudi lawyer (licence 46592)
Send a short summary. The office reviews your inquiry, then contacts you to discuss the service and fees.
Many subcontract disputes in the Jubail and Dammam industrial area start with a one-page purchase order or a short subcontract copied from another project. When the main contract and the subcontract do not fit together, the subcontractor usually carries the gap.
This page sets out the clauses that matter most, for subcontractors and main contractors alike, under the Civil Transactions Law.
We draft and review subcontracts for contractors in Jubail, Jubail Industrial City, Dammam and Khobar.
The legal background
The Civil Transactions Law's contracting (muqawala) provisions apply to subcontracts:
- the law addresses unit-rate and lump-sum pricing;
- The Civil Transactions Law addresses the right to subcontract and the employer's limited liability to subcontractors;
- The law deals with correcting defective work and with termination where a breach cannot be rectified.
What the subcontract says still decides most disputes.
1. Scope and documents
Define the scope precisely, with drawings, specifications and a bill of quantities attached. If parts of the main contract are "incorporated", list exactly which clauses, and make sure the subcontractor has actually received them.
2. Price and measurement
- Unit rates: set the measurement method and who signs the measurement sheets, and how often.
- Lump sum: define what is included and what counts as a change. Under the contracting rules, general exceptional circumstances that destroy the contract's balance may allow the court to extend time, adjust the price or terminate.
3. Payment terms
- Set the payment cycle, the certification steps and the due date after each step.
- If you use a "pay when paid" or "pay if paid" link to the owner, define it carefully: what happens if the owner certifies but does not pay, and what happens if the delay is caused by the main contractor.
- Retention: state the percentage, when it is released, and what triggers release.
- Avoid fixed late-payment penalties on unpaid sums. The Civil Transactions Law allows agreed compensation, except where the obligation is to pay a sum of money.
4. Variations
Require written instructions for variations, set a short period for pricing them, and state how disputed variations are paid in the meantime. Most variation disputes are lost for lack of a written instruction.
5. Delay and liquidated damages
Back-to-back delay damages are common, but they must be realistic:
- agreed compensation is not payable if the debtor proves no harm;
- it can be reduced if exaggerated, or if the obligation was partly performed.
Set a rate and a cap, and link extensions of time in the main contract to the subcontract.
6. Defects
Set an inspection and snagging process. Under the contracting rules, the employer may require correction within a reasonable time, failing which a third party may do the work at the contractor's expense. A clear notice-and-cure clause applies this to the subcontract chain.
7. Termination
- If you want a right to terminate without a court order, say so expressly.
- Otherwise, a party notifies the other and asks the court to rescind for non-performance.
- If a breach cannot be rectified, or cannot be rectified within the agreed period, the employer may demand immediate termination.
- Dispute-resolution and confidentiality obligations survive rescission unless agreed otherwise.
8. Security and disputes
- Payment security that can be enforced directly includes cheques and registered promissory notes.
- If you choose arbitration, use a clear clause. A valid arbitration clause stops the court from hearing the dispute if the defendant relies on it.
Example: A mechanical subcontractor in Jubail Industrial City is offered a subcontract with delay damages of 1% per day and no cap, and payment only "after receipt of payment from the client". On review, it negotiates a cap, a defined period after owner certification within which payment is due regardless, and written variation instructions with a seven-day pricing period.
FAQ
What should a subcontract in Saudi Arabia include?
Scope documents, a price and measurement method, payment and certification terms, variations, delay damages with a cap, defects, termination, security and a dispute clause.
Are back-to-back clauses enforceable?
They can be, if the incorporated terms are clearly identified and provided to the subcontractor. Delay damages remain subject to the agreed-compensation rules.
Can a subcontractor claim directly from the project owner?
Only in limited circumstances. The Civil Transactions Law addresses this.
Can a subcontract be terminated without court?
Only if it expressly allows rescission without a court order. Otherwise, ask the court.
Is retention money legal in Saudi Arabia?
Retention is a contractual term. State the percentage, release triggers and dates clearly, so it can be claimed when due.
Talk to us
Send us the subcontract, or the purchase order and the main contract terms. Our office is in Al Jubail, and we act for contractors across the Eastern Province.
Message us on WhatsApp +966 55 726 8709.
Related: Subcontractor Payment Claims · Construction Contract Disputes · Contract Drafting and Review
This page is general information, not legal advice. For advice on your specific case, contact us.